Project Name | Project Location | Name of Client | Project Status | Date of Completion | Project Overview |
---|---|---|---|---|---|
Road Rehabilitation and Overlay work at Lalitpur District | Lalitpur | DoR | On Going | 9.303 km Blacktop Road [Dolakha] | |
Upgrading and Performance Based Maintenance of Roads in Dolakha, Sindhupalchowk and Kavrepalanchowk | Dolakha, Sindhupalchowk and Kavrepalanchowk | DoLIAR, RCIP | On Going | 12.083 km road [Dolakha] 12.377 km road [Sindhupalchowk] 18.629 km road [Kavrepalanchowk] |
|
Reconstruction & Rehabilitation of Godamchaur-Godabari-Badikhel-Lele Bhanjyang, Lalitpur Road | Lalitpur | EEAP, CLPIU | On Going | 14.4 km road [7 km Asphalt Concrete Paved and 7.4 km Graveled] | |
Road Safety Works at Sitapati Musikot Road [RSDP] | Dang | Division Road Office [DRO] -Dang | On Going | Ch 52+650 km to Ch 138+120 km Highway | |
Improvement of Lainchaur-Balaju Road | Kathmandu | Division Road Office [DRO] -Kathmandu-2 | Completed | 14.07.2016 | Balaju Chowk Asphalt Concrete 140m Rigid Pavement at Sorhakhutte |
Supply and Installation of Steel W-Beam Crash Barrier (Road Safety Works) on Sitalpati-Musikot, Chinchhu-Jajarkot & Surkhet-Tallodhungeshwor-Dailekh Road [RSSP] | Nepal | Foreign Corporation Branch, DOR, Babarmahal, Kathmandu | On Going | Road Safety Works | |
Strengthening of Runway, Taxiway, Apron (Aphalt Concrete) and other associated works at Rara Airport | Rara, Mugu | Civil Aviation Authority of Nepal | Completed | 12.04.2016 | Asphalt Concrete: 749.43 cu.m Sub-base: 4571.64 cu.m Crushed Stone Base: 2248.281 cu.m Gabion Work: 3990 cu.m |
Asphalt Road Maintenance Work on Naubise Piplamod Section of TRP | Bharatpur | Division Road Office [DRO] -Bharatpur | Completed | 30.06.2015 | Ch 14+400 to Ch 24+400 km Asphalt Road Maintenance |
Bridge Construction Work at Kul Khola, Okhaldhunga | Okhaldhunga | Local Roads Bridge Programme | On Going | Single Span RCC Motorable 20.3 m bridge | |
Rehabilitation and Upgrading of Road including Footpath & other Road Furniture Works in Singhadurbar Premises | Kathmandu | DOR, Kathmandu Valley Road Improvement Project | Completed | 23.11.2014 | Earthworks in Excavation and Filling: 1419.28 cu.m Graded Crushed Stone Base: 951 cu.m Asphalt Concrete: 1637.72 cu.m |
Improvement of Tinkune-Airport-Gaushala Road | Kathmandu [km 0+000 to km 3+617] | DOR, Kathmandu Valley Road Improvement Project | Completed | 23.11.2014 | Earthworks in Excavation and Filling: 7129.81 cu.m Crusher Run Subbase: 2215.92 cu.m Graded Crushed Stone Base: 4406.71 cu.m Asphalt Concrete + DBM: [3340.85 + 454.16] cu.m |
Asphalt Concrete Road work & Hume Pipe laying work | Varun Developers Pvt. Ltd. | Completed | 26.09.2013 | Asphalt concrete, Hume pipe work | |
Periodic Maintenance of Birtamod-Chandrgadhi Road, Mechi Highway | Damak | Eastern Regional Roads Directorate, Damak | Completed | 24.06.2012 | Road work |
Periodic Maintenance of East West Highway | Damak | Eastern Regional Roads Directorate, Damak | Completed | 24.06.2012 | Road work |
Periodic Maintenance of Peepalmod-Nagdhunga, Kalanki-Tripureswor-Balaju Ring Road, Balaju Ring Road-Balaju Bypass, Nagdhunga-Tankeswor | Kathmandu [km 145+198 to km 147+183] | DOR, Program Coordinator, Road Sector Development Project (RSDP) Kathmandu | Completed | 15.07.2013 | Asphalt Concrete/Bituminous Macadam: 2741.77 cu.m Premix Carpet Work: 40.35 cu.m |
Pavement Strengthening & Road Widening Works with Footpath Construction for a Section in Thirbam Marg | Kathmandu [km 1+550 to km 3+230] | Kathmandu Valley Road Improvement Project | Completed | 20.12.2012 | Earthworks in Excavation: 4931.36 cu.m Asphalt Concrete + DBM: [3340.85 + 454.16] cu.m Single Butiminous Surface Dressing: 18790.90 cu.m Interlocking Tile: 1017.73 cu.m Hume Pipe Work: 889.90 Rm |
Periodic Maintenance of Dumre-Muse Khola (108+220-113+000), Dumre-Bandipur (0+000-8+000) and Khairenitar (PRM)-Bhimad-Ghumarighat (Khaireni Bhimad sector) (0+000-5+000) | Pokhara | Western Regional Roads Directorate, Pokhara | Completed | 08.07.2013 | Surface Dressing (Bituminous works): 72268 sq.m Base Course: 684.24 cu.m Semi Grouting [50mm thick]: 2387.30 sq.m Premix Patching Works: 15177.19 sq.m |
Periodic Maintenance Kotre-Bijayapur Khola(154+540 – 158+500) , Kaligandaki-Waling(87+740 – 118+450) and Pokhara Mu boundary-Prithivi Chowk(178+770 – 183+190) | Pokhara | Western Regional Roads Directorate, Pokhara | Completed | 09.07.2012 | Surface Dressing (Bituminous works): 224215.61 sq.m Base Course: 1369 cu.m Sub Base: 585.43 cu.m Premix Patching Works: 16598.52 cu.m |
Construction and Improvement of Naudanda–Kaskikot-Sarangkot Road | Kaski | Office of DDC, District Technical Office, Kaski | Completed | 08.01.2013 | Gravelling Work of 11.3 km with Gabion Retaining Earthworks in Excavation: 20949 cu.m Sub Grade Preparation: 44018 sq.m Sub Base Work, Stone Masonry, Gabion Masonary Work |
Construction of Motorable RCC Bridge over Madi River | Kaski | Western Regional Road Directorate, Damauli | Completed | 24.06.2013 | Total Length of 85.95 m with Bridge span = 21m, Open Foundation Earthworks in Excavation and Filling: 10494.5 cu.m Concrete Works: 1142.45 cu.m |
Periodic Maintenance Work of Pokhara Baglung Road and Pokhara Sarangkot Road | Pokhara, Kaski | Western Division Road Office No. 2, Pokhara | Completed | 29.06.2012 | Resealing Surface Area: 190675 sq.m |
Reconstruction and Rehabilitation Work of Dovilla-Phalebas Rural Road (Package II) | Parbat [Ch 8+500 to Ch 15+955] | DDC, District Project Office, Parbat | Completed | 13.05.2012 | Earthworks in Excavation: 26067 cu.m Stone Masonry: 3780 cu.m Gabion Work: 2340 cu.m |
Surface dressing work of Dhakadhai–Bishnupura Road | Rupandehi [Ch 0+000 to Ch 7+000] | District Technical Office, Rupandehi | Completed | 03.08.2010 | Earthworks: 24955.2 cu.m Sub Grade Preparation: 26864 sq.m Sub Base Work: 5404.6 cu.m First Coat Surface Dressing: 23662.7 sq.m Second Coat Surface Dressing: 23369.5 sq.m |
Surface dressing work of Hatibangai-Marchwar Road | Rupandehi [Ch 7+000 to Ch 14+000] | District Technical Office, Rupandehi | Completed | 03.09.2010 | Earthworks: 3758.95 cu.m Sub Grade Preparation: 36989.25 sq.m Sub Base Work: 6691.7 cu.m First Coat Surface Dressing: 29618.33 sq.m Second Coat Surface Dressing: 29366.75 sq.m |
Periodic Maintenance Work of Prithvi Highway & Dhumre-Beshisahar | Prithivi Highway from km 113+150 to km 121+150 Dumre-Besisahar from km 19+570 to km 26+570 |
Western Division Road Office No.1 Damauli, Tanahun | Completed | 13.06.2010 | Surface Dressing Work: 73825 sq.m Stone Masonry Work: 225.61 cu.m Bituminous Premix: 52.76 cu.m |
Bishnumati Link Road Upgrading Sub-Project (Teku Bridge Junction-Sorhakhutte Junction) | Kathmandu [km 0+000 to km 2+800] | Kathmandu MPC, Urban & Environmental Improvement Project | Completed | 15.03.2010 | 2.8 km Road Upgrading Earthworks in Excavation: 12218.69 cu.m Road Works, Interlocking Tile Work, Hume Pipe Work, Drain Works |
Upgrading of Satbanjh-Gokuleshwor Road (Contract No. RSDP/NCB/SG-07) | Baitadi [km 0+000 to km 19+000] | Road Sector Development Project, DOR | Completed | 26.03.2010 | 19 km Road Upgrading Earthworks in Excavation: 81705.44 cu.m Stone Masonry: 11660.54 cu.m Gabion, Sub-Surface Drainage, Otta Seal, Sand Seal |
Upgrading of Satbanjh-Gokuleshwor Road (Contract No. RSDP/NCB/SG-08A) | Baitadi [km 19+000 to km 28+700] | Road Sector Development Project, DOR | Completed | 31.12.2009 | 9.7 km Road Upgrading Earthworks in Excavation: 46335.48 cu.m Stone Masonry: 5712.34 cu.m Gabion, Sub-Surface Drainage, Otta Seal, Sand Seal |
Surface dressing work in Ratna Rajmarg (Deurali-Harre) | Banke | Division Road Office No.3, Banke | Completed | 14.11.2008 | Surface Dressing Work: 72570.10 sq.m Slurry Seal: 2001.30 sq.m Shoulder Gravel: 14716.97 sq.m |
Road Improvement Component of Mudhe Sanischare – Khandbari Road | Sankhuwasabha | Project Directorate (ADB), Department of Roads | Completed | 24.03.2009 | Earthworks in Excavation: 31167 cu.m Bio-Engineering Works: 21522 sq.m Sub Base Work: 3284 cu.m Hume Pipe Work: 150 Rm |
Construction of Sunkoshi River Bridge | NCCN | Completed | 09.07.2007 | Truss Bridge (Bridge span=48m*2Nos.) with Well Foundation Bridge Width: 5.25m |
|
Fireline-Lumbini Road (Contract No. RAIDP/RUP/PCK-B/SL-1/063/64) |
Rupandehi | DDC, Rupandehi | Completed | 20.05.2008 | Otta Seal Work (Length 7.5 km, Width 6 m) |
Fireline-Lumbini Road (Contract No. RAIDP/RUP/PCK-B/SL-2/063/64) |
Rupandehi | DDC, Rupandehi | Completed | 30.05.2008 | Otta Seal Work (Length 7.0 km, Width 6 m) |
Road Improvement Project, Khimti Hydropower Plant | Ramechhap | Himal Power Limited | Completed | 22.09.2006 | Road Work, Fencing (Chain Link), Stone Masonry Boundary wall |
Pashupati Core Area Development Project | Kathmandu | NCCN | Completed | 13.06.2006 | Water supply, Drainage, Road & Landscaping Works |
Narayanghat-Mugling Highway Rehabilitation Project | Dhading [km 8+000 to km 24+000] | Central Division Road Office No. 8, Department of Roads | Completed | 29.04.2006 | 16 km Highway Earth Works: 216249.1 cu.m Stone Masonry: 5309.43 cu.m Gravelling Work, Base Course, Semi Grouting, Asphalt Concreting, Gabion Retaining Wall Structure |
Najdhunga Checking Bay Construction Project (Contract No. 6/061/62) |
Kathmandu | Division Road Office, Minbhawan, Kathmandu Department of Roads |
Completed | 27.11.2005 | Stone Masonry, Gravelling Work, Base Course, Semi Grouting, Asphalt Concreting, Gabion Retaining Wall Structure |
Najdhunga Checking Bay Construction Project (Contract No. 7/061/62) |
Kathmandu | Division Road Office, Minbhawan, Kathmandu Department of Roads |
Completed | 27.11.2005 | Stone Masonry, Gravelling Work, Base Course, Semi Grouting, Asphalt Concreting, Gabion Retaining Wall Structure |
Chabahil-Gaushala-Baneshwor Chowk Extension and Development Project | Kathmandu | Division Road Office, Minbhawan, Kathmandu Department of Roads |
Completed | 13.12.2005 | Semi grouting, Premix. Asphalt Concreting, PCC, Brick Masonry, Stone Masonry |